HOSPITALMaster Plan Validation Study
Validating a new Hospital Building Master Plan
Key Points
- Future state plan validation
- VA NVA identification to shorten lead time
- Impact of change in distance between departments
- The new facility should accommodate the projected number of patients
- Bed/resource requirements
- Identification and quantification of bottleneck areas
- It can help in adding more space/counters in these areas
- Visualizing the entire hospital if integrated
- Analysis of Data, building the model, and verification
- Separate models made for each department
- Analysis of baseline model results
- Bottleneck identification
- Individual models' integration
- Layout distance sensitivity analysis
Findings & Recommendation
- Hospital capacity (to serve 61000 patients/year) validated
- The integrated model was found to have concerns in Common rooms
(named RIO)
- RIO was found to be the bottleneck due to its capacity, and
Patient In-System Stay time (lead Time)
- Existing RIO capacity increased by 5 beds
Let our experts show you how our Services can support your projects!
Send a message to our team by filling out the form below. Describe your project, ask questions, or even request a bid.
An expert from our team will be in touch with you within one business day!
Want to schedule a time to speak with one of our representatives NOW?