One of India’s leading tyre manufacturers planned to install a conveyor system to replace manual trolleys that carried tyres through Tyre Building Machines (TBM), Curing Machines (TCMs) and Inspection stations.
Key Points
- Tyre Industry
- AutoMod
- Bottleneck Analysis
- Feasibility Study
- Buffer Analysis
- Check feasibility and validate the proposal
- Identify and alleviate bottlenecks in the system
- Recommend alternatives design proposals if required
We carried out static analysis and 3D simulation to study in detail:
- TBM à TCM Sub-system with overhead conveyors measuring 600 meters in length
- TCM à Inspection Sub-system with similar features
Findings & Recommendations
We were able to identify that the client’s proposal would meet only about 30 % of their monthly target due to:
- Insufficient number of empty hangers available at tyre building machines, reducing tyre supply into the system
- Mismatch in production and consumption at TBMs and TCMs
After experimenting with several what-if scenarios, we recommended the following changes to achieve their target
- A hybrid centralized buffer system of 3000 tyre capacity with defined rules for operation
- Minimum buffer to be used near tyre curing machines and inspection
- Optimum hanger speed and number of carriers to be used in the system
Let our experts show you how our Services can support your projects!
Send a message to our team by filling out the form below. Describe your project, ask questions, or even request a bid.
An expert from our team will be in touch with you within one business day!
Want to schedule a time to speak with one of our representatives NOW?