Work Content Estimation & Manpower Calculation (Stores Operations)
February 6, 2023Work Content Estimation and Manpower Optimization (Marketing Operations)
February 6, 2023
Work Content Estimation & Manpower Optimization - Indirect Areas Case Study
Key Points
- Work content measurement of indirect area
- Optimum use of Manpower/Resource
- Work Content Estimation for : Machine cleaning, Housekeeping/Sanitation, Horticulture, Security, R&D
- Manpower Calculation & Work distribution
- Suggestions & improvement for manpower optimization
- Prepared formats for data collection at each areas
- Sampling observation & video shooting for each area
- Work content estimation using Video time study, work sampling, etc.
- VA, NVA, SVA Analysis of repetitive/non-repetitive activities
- Master activity sheet generation for each area
Results
- Work content with master activity sheet - helps to calculate manpower if any changes in activity time
Let our experts show you how our Services can support your projects!
Send a message to our team by filling out the form below. Describe your project, ask questions, or even request a bid.
An expert from our team will be in touch with you within one business day!
Want to schedule a time to speak with one of our representatives NOW?